Daily Plant Pre-Use Check

AMWS — Daily Plant Pre-Use Check (FORM_PRE_USE_PLANT_01)

Daily walk-around check for plant + equipment.

This field is for validation purposes and should be left unchanged.

AMWS — Daily Plant Pre-Use Check (FORM_PRE_USE_PLANT_01)

Daily walk-around check for plant + equipment (excavators, breakers, generators, etc.). Separate from the van checks (QA_FM_08 / 09).

Document ReferenceFORM_PRE_USE_PLANT_01 — Daily Plant Pre-Use Check
Issue Number1
Issue Date12 May 2026
Next Review12 May 2027
Controlled BySean Ashton (HSQE Consultant, Onyx Operations)
Approved ByAaron Mason, Managing Director
StatusNew controlled document — supports B2.14.1.
DD slash MM slash YYYY
Please enter a number from 0 to 999999.

Pre-use checks

Visual condition — no obvious damage(Required)
Tyres / tracks in good condition(Required)
Fluids OK (oil, hydraulic, coolant, fuel)(Required)
No leaks (fuel, hydraulic, oil)(Required)
Lights and warning beacons working(Required)
Horn / reversing alarm working(Required)
Seat belt + ROPS/FOPS structure intact(Required)
Controls labelled + functioning(Required)
Brakes effective(Required)
Emergency stop accessible + tested(Required)
Operator manual on the machine(Required)
Statutory inspection in date (LOLER/PUWER)(Required)
Drop files here or
Accepted file types: jpg, jpeg, png, heic, pdf, Max. file size: 5 MB, Max. files: 5.
    Clear Signature